Scope of work:
- Dismounting of old BWTS system.
- BWTS system installation.
- 3D Design works for new pipelines.
Piping systems installed:
- Ballast piping.
- Air supply lines to new equipment and valves.
- Fresh water cooling.
- Backflush piping.
- Pressure tests of the installed piping.
Steelworks:
- Prefabrication of foundations and platforms for the new equipment.
- Overboard pipe installation